Room Integrity Testing – Frequently Asked Question

We have collated some of the most frequently asked questions related to Room Integrity Testing. We hope it helps to you to understand the requirements of BS EN 15004.

Why do I need a room integrity test on my server room?
A - The test is a requirement of the British Standard for gaseous fire extinguishing systems – BS EN:ISO 14520. Most fire insurers will require evidence that the test has been conducted and the result is satisfactory.

How quickly can a room integrity test be arranged?
A - Usually within a few days.

How long does the enclosure test take?
A - Usually between 1 and 2 hours.

Will the server room integrity test set off alarms?
A - No. The enclosure test is completely independent of the detection system.

Is the room integrity test disruptive?
A - No. It is only necessary to stop access to the room for 10-15 minutes. Personnel can continue to work in the room. The enclosure test can be paused if immediate access becomes required.

Do servers need to be switched off during the enclosure integrity test?
A - No the equipment can keep running.

Do air conditioning units need to be switched off during the enclosure integrity test?
A - Recirculation (chiller) units may continue to run. Air supply/extract ducts passing into the enclosure will need the dampers closed or temporarily sealed.

Will I get a certificate if I pass the room integrity test?
A - It will be issued within a few days. This should be retained for possible inspection by the authorities/insurers. A summary certificate can be issued at the time of enclosure test if required.

Where do I store the pass certificate?
A –It is a good idea to laminate the certificate and then attach it to the front of the enclosure door, as it lets the fire officer know when the next annual test should be undertaken.

What happens if the room fails the server room enclosure test?
A - We can carry out an inspection to identify leakage paths for remedial sealing. These will be pointed out at the time of the enclosure test and a plan included in the report. It is recommended that a retest be conducted after remedial action to confirm the adequacy of the retention time.

Can remedial sealing be done at the time of the server room enclosure test? - Yes, provided the leakage can be swiftly remedially, or temporarily, sealed.

Can APT undertake remedial sealing?
A- Yes we can do this if requested or the client can arrange remedial sealing themselves.

Do you supply any literature to help us prepare for the enclosure test?
A - Yes, we supply all our clients with an easy to follow checklist to help them prepare for the room enclosure test.

How often should the room integrity test be undertaken?
A - The relevant British Standard (BS EN:ISO 14520) specifies that the test should be conducted annually as part of routine maintenance and/or after works have taken place to the enclosure envelope.


If you would like more information in regards to a server room integrity test, please contact us now at info@airpressuretesting.net or call us on 07775623464.